Keates Lane Roadworks from Jan 14th

December 19, 2018

Here is a description of the planned works due to commence on the 14th of January 2019.

 

As previously discussed, this is an essential traffic signal refurbishment scheme with additional road safety benefits for pedestrians and cyclists, and as such deemed to be essential highway works hence there will be no broader public consultation. 

 

There are SIX documents which contain all of the information about the works - Click on the documents in the list below to read them:-

  1. Keates Lane Eton - Residents Notification

  2. VH1633 KEATS LANE JNC HIGH ST WINDSOR

  3. VH1633 KEATS LANE JNC HIGH ST WINDSOR 2

  4. VH1633 KEATS LANE JNC HIGH ST WINDSOR 3

  5. VH1633 KEATS LANE JNC HIGH ST WINDSOR 4

  6. SLE-115A

 

These works are carried out in 3 stages;

  • Phase 1: Commencing on 14/01/19 for 2 weeks under 3-way temporary traffic signals

  • Phase 2: Commencing on 28/01/19 for 2 weeks under 3-way temporary traffic signals.

  • Phase 3: Commencing on 11/02/19 for 2 weeks under road closure.

Also attached are diversion route plans which can also be found on Roadworks.org.

 

As the works are commencing on the 14th of January, RBWM will communicate this information on our social media  from the 2nd/3rd of January. In addition, Volkers would put up all advanced road signs and Variable Message Signs from the 1st week of January to pre inform the public. All enquiries are directed to our Customer Service Center on 01628 683868 or email Highways@rbwm.gov.uk

Please reload

Featured Posts

The Eton Action List

December 3, 2019

1/5
Please reload

Recent Posts

December 5, 2019

December 3, 2019

November 27, 2019

October 1, 2019

Please reload

Archive