High Street Gas project update

Here we go again!! The Gas Works are now continuing... and Mick and Bernie are back with us! Let’s hope the process will run at or ahead of plan! Here's the latest update (30th July)


"We (tRIIO) are completing our first 50m section of engineering works tomorrow (Thurs 30th) since returning to site and will be reinstating over the weekend in order to move our 2 way traffic lights further up the High Street to begin works on the next section which is planned in towards the end of next week

All residents have been extremely welcoming and helpful since our return to site and we will continue to work with them to ensure we complete these works with as little disruption as possible"




Site Manager

tRIIO® c/o Cadent, Brunel House Uxbridge Road, Slough

Berkshire, SL2 5NA


More info: contact the Project Manager

Richard Penny

Project Manager – London West MRP

Mobile: 07464 489958



Copyright Eton Community Association 2017 

PARTNERS
VISITORS